11.13.2014 Release Notes

Follow

Comments

2 comments

  • Avatar
    Brea Engel

    Is there a way to apply a different indirect rate to an individual grant award than the standard rate than the organization negotiated?

    0
    Comment actions Permalink
  • Avatar
    Christy Pellegrino

    Yes; to edit a particular grant's indirect cost rate, go to the grant, then using either the Pre-Award tab or Post-Award tab (depending on where this grant is at in its life), click on Budget Settings. From here, you'll click the pencil icon in the top right corner to input a different indirect cost rate. Once entered, you may click the Update button at the bottom right.

    0
    Comment actions Permalink